07/08/2014
DCC Urged To Terminate Poolbeg Incinerator Project
Dublin City Council's Chief Executive, Owen Keegan, has been urged to end the contract for the construction of the Poolbeg Incinerator.
The Chief Executive had previously said that a decision on the incinerator would be made following an EU ruling on two complaints made about the project.
However, Councillor O'Callaghan points out that the EU ruling was made three months ago yet no decision has be given on the Poolbeg Incinerator.
"The European Commission ruled three months ago on 7 May that the Poolbeg Incinerator project did not breach State Aid rules. The Chief Executive told Councillors that a decision on the future of the Incinerator would be made following the ruling.
"Three months have now passed and no decision has been made. The Chief Executive needs to scrap this wasteful project promptly. The longer this indecision proceeds the greater will be the financial drain on the city.
"To date over €100 million has been spent on this project which was planned for a different era. A project of this size will deter recycling and have a detrimental impact on one of Dublin's most scenic areas. The Chief Executive needs to heed the views of the elected representatives of Dublin City who have consistently opposed this project."
(MH/JP)
The Chief Executive had previously said that a decision on the incinerator would be made following an EU ruling on two complaints made about the project.
However, Councillor O'Callaghan points out that the EU ruling was made three months ago yet no decision has be given on the Poolbeg Incinerator.
"The European Commission ruled three months ago on 7 May that the Poolbeg Incinerator project did not breach State Aid rules. The Chief Executive told Councillors that a decision on the future of the Incinerator would be made following the ruling.
"Three months have now passed and no decision has been made. The Chief Executive needs to scrap this wasteful project promptly. The longer this indecision proceeds the greater will be the financial drain on the city.
"To date over €100 million has been spent on this project which was planned for a different era. A project of this size will deter recycling and have a detrimental impact on one of Dublin's most scenic areas. The Chief Executive needs to heed the views of the elected representatives of Dublin City who have consistently opposed this project."
(MH/JP)
Related Irish News Stories
Click here for the latest headlines.
07 May 2014
Poolbeg Incinerator Did Not Break State Aid Rules - Eu Commission
The European Commission has ruled that the Poolbeg Incinerator project did not breach rules on state aid, and will continue on market terms. However, the project is still facing a second complaint over public procurement procedures, and will be cancelled should the ruling go against it.
Poolbeg Incinerator Did Not Break State Aid Rules - Eu Commission
The European Commission has ruled that the Poolbeg Incinerator project did not breach rules on state aid, and will continue on market terms. However, the project is still facing a second complaint over public procurement procedures, and will be cancelled should the ruling go against it.
22 July 2010
€350m Poolbeg Incinerator Halted
Construction has halted on Dublin's Poolbeg incinerator after the Department of the Environment failed to approve a foreshore licence. The Department is yet to process an application lodged in December 2008 for an out-flow pipe into the sea. Work on the €350m facility can't resume until the license is granted.
€350m Poolbeg Incinerator Halted
Construction has halted on Dublin's Poolbeg incinerator after the Department of the Environment failed to approve a foreshore licence. The Department is yet to process an application lodged in December 2008 for an out-flow pipe into the sea. Work on the €350m facility can't resume until the license is granted.
08 January 2014
Minister Urges Govt To Take Health Concerns Surrounding Eirgrid Project Seriously
Sinn Féin's EU candidate for the constituency of Ireland South, Liadh Ní Riada, has today called on the government to take the health concerns surrounding the EirGrid Grid Link project seriously.
Minister Urges Govt To Take Health Concerns Surrounding Eirgrid Project Seriously
Sinn Féin's EU candidate for the constituency of Ireland South, Liadh Ní Riada, has today called on the government to take the health concerns surrounding the EirGrid Grid Link project seriously.
07 January 2014
New Interim Head Appointed To Limerick City Of Culture Project
Mike Fitzpatrick has been appointed as the interim head of the Limerick City of Culture project. He will take over the post following the recent resignations of Chief Executive, Patricia Ryan, and artistic director Karl Wallace.
New Interim Head Appointed To Limerick City Of Culture Project
Mike Fitzpatrick has been appointed as the interim head of the Limerick City of Culture project. He will take over the post following the recent resignations of Chief Executive, Patricia Ryan, and artistic director Karl Wallace.
11 January 2010
Incinerator Still Inflames Community
As many as 500 construction jobs may be in doubt as the building of a highly controversial 600,000 tonne waste incinerator in Dublin's Poolbeg continues to be debated. It has now emerged that any so-called interference with the project could leave the Irish State facing a multimillion euro compensation bill.
Incinerator Still Inflames Community
As many as 500 construction jobs may be in doubt as the building of a highly controversial 600,000 tonne waste incinerator in Dublin's Poolbeg continues to be debated. It has now emerged that any so-called interference with the project could leave the Irish State facing a multimillion euro compensation bill.